Appendix A : Guide To Time Taken To Grant Approval Of Structural Plans & Permit to Carry Out Structural Works
The following time frames for approval of structural plans are only a general guide since each submission can vary greatly in terms of complexity. Complete and good quality submissions which do not require written directions to be issued and complied with, as well as quick response and compliance to written directions by qualified person will facilitate the process and shorten the time taken for approval of plans.
The general guide on the time taken to respond to applications for approval of structural plans are as follows:-
| 1. |
Projects where an accredited checker's certificate is not required. |
7 |
| 2. |
Projects where an accredited checker's certificate is required. |
14 |
| 3. |
Permit to carry out structural works |
7 |
You can apply for a permit together with your application for approval of structural plans or after obtaining the plan approval.
|